Pittsburgh, PA
Project Details:
PROBLEM: Condensation of the roof deck and high utility cost.
SOLUTION: Using our spray foam insulation equipment and our highly trained and certified installation experts we were able to give Z-Con, Inc the protection necessary to eliminate the condensation on the roof deck that was wasting them money and putting their employees and production time and equipment at risk. InsulRIght has proven that we know how to control condensation and airflow in most any building type.
SPECS:
Average of 3″ Open Cell Foam applied directly to the corrugated metal deck.
The maximum working height was 85′.
Due to time constraints, insulRight mobilized 3 rigs and lifts to accommodate 92,000 SF of surface coverage in 20 days.